Broadway Subway Trains Start Rolling: What Late 2027 Opening Means for Mount Pleasant, Kitsilano & Arbutus Buyers
Share
News article poster

The first test train is now rolling on the Broadway Subway. On May 29, 2026, provincial officials including Transportation Minister Mike Farnworth joined media for a ride-along on two retired Mark I SkyTrain cars—the 013 and 014 units—traveling along the new 0.7-km elevated guideway through False Creek Flats. This marks the beginning of dynamic testing for SkyTrain's 5.7-km Millennium Line extension from VCC-Clark Station to Arbutus Street, a $2.95-billion project that has now shifted from construction to systems verification. The initial testing covers approximately two kilometers of track between the elevated segment west of VCC-Clark and a short underground portion west of the new Great Northern Way-Emily Carr Station, the most advanced section where running rails, power rails, and linear induction motor strips are fully installed.